Title:
|
Resolution authorizing the General Manager of the San Francisco Public Utilities Commission to execute Amendment No. 3 to the New Headworks Facility Construction Management Staff Augmentation Services Agreement PRO.0028 with HDR Engineering Inc.; increasing the agreement by $4,680,626 for a total not to exceed amount of $31,680,626 and extending the duration by one year, for a total term of eight years and six months of June 15, 2017, through December 14, 2025, to reflect the re-scoping efforts and increased level of staffing needed to complete the construction of the Southeast Water Pollution Control Plant New Headworks Facility, pursuant to Charter, Section 9.118.
|