Title:
|
Resolution authorizing the General Manager of the San Francisco Public Utilities Commission to execute Amendment No. 5 to Agreement No. CS-820, New Irvington Tunnel Project, Engineering Services, with URS Corporation, in order to allow URS Corporation to continue as design engineer of record for the construction of the tunnel, increasing the agreement amount by $1,000,000 for a total amount not to exceed $15,873,561 with no change to the contract duration, pursuant to Charter, Section 9.118.
|