City Hall
1 Dr. Carlton B. Goodlett
Place
San Francisco, CA 94102-
4689
City and County of San Francisco
Legislation Details
File #:
Version:
1
091037
Name:
Settlement of Lawsuit and Disputes and Agreement
to Close the Potrero Power Plant - $1,100,000
Status:
Type:
Ordinance
Passed
File created:
In control:
8/18/2009
Board of Supervisors
On agenda:
Final action:
11/6/2009
Enactment date:
220-09
Enactment #:
Title:
Ordinance authorizing settlement of the lawsuit filed by the City and County of San Francisco against
Mirant Potrero L.L.C. on April 27, 2009, in San Francisco Superior Court, Case No. CGC 09-487-795;
entitled City and County of San Francisco, et al., v. Mirant Potrero L.L.C., which settlement provides
for, among other things, permanent closure of the entire Potrero Power Plant when it is no longer
needed for electric reliability, payment by Mirant of $1,100,000 to the City, the City's agreement to stay
enforcement of the UMB Ordinance for the unoccupied unreinforced masonry buildings located at the
Potrero Power Plant site pending a new site reuse plan so long as Mirant maintains the buildings in a
safe manner, Mirant's agreement to restrict future uses of the site to prohibit fossil fuel generation
after the Plant is shut down, and the City's agreement to priority processing of a future application for
entitlements for a proposed site reuse plan.
Sponsors:
Sophie Maxwell, David Chiu, Michela Alioto-Pier
Attachments:
1. Leg_Ver1, 2. Leg_Final
Action By
Date
Action
Result
Ver.
RECEIVED AND ASSIGNED
President
8/18/2009
1
RECOMMENDED AS COMMITTEE
REPORT
Rules Committee
10/15/2009
1
Pass
PASSED, ON FIRST READING
Board of Supervisors
10/20/2009
1
Pass
FINALLY PASSED
Board of Supervisors
10/27/2009
1
Pass
APPROVED
Mayor
11/6/2009
1