Name:
Contract Amendments - Central Subway Design
Group - Central Subway Project - Not to Exceed
$47,900,606
Status:
Type:
Resolution
Passed
File created:
In control:
6/12/2018
Clerk of the Board
On agenda:
Final action:
6/12/2018
6/28/2018
Enactment date:
6/28/2018
219-18
Enactment #:
Title:
Resolution retroactively approving Amendment No. 1 and approving Amendment No. 4 to Contract CS
-155-2 Architectural and Engineering Services for the Final Design and Construction of the Central
Subway Project with Central Subway Design Group to increase the contract amount by $1,010,600 for
Amendment No. 1 for designs to lower the Chinatown Station, and $6,323,936 for Amendment No. 4
for additional work necessary to provide engineering services through completion of the Central
Subway Project stations construction, with no change to the length of the 10-year term to expire on
April 4, 2020, for a total amended contract amount not to exceed $47,900,606.
Sponsors:
Attachments:
1. Leg Ver1, 2. DRAFT Contract Amend No. 4, 3. Contract Amend No. 3 110416, 4. Contract Amend
No. 2 031516, 5. Contract Amend No. 1, 6. Contract CS-155-2 120109, 7. MTA CEQA Determination
042718, 8. MTA Briefing Ltr 060118, 9. SFMTA Reso No. 180605-90 060518, 10. DRAFT MTA Reso,
11. MTA Ltr 060118, 12. Form 126, 13. BLA Rpt 062018, 14. Comm Pkt 062018, 15. Board Pkt
062618, 16. Form 126 Final, 17. Leg Final
Action By
Date
Action
Result
Ver.
RECEIVED FROM DEPARTMENT
Clerk of the Board
6/4/2018
1
RECEIVED AND ASSIGNED
President
6/12/2018
1
RECOMMENDED
Government Audit and Oversight
Committee
6/20/2018
1
Pass
ADOPTED
Board of Supervisors
6/26/2018
1
Pass
APPROVED
Mayor
6/28/2018
1