File #:
Version:
1
210338
Name:
Contract Modification - Thales Transport & Security
Inc. - Advanced Train Control System for Central
Subway - Increase Contract Amount - Not to Exceed
$27,730,300.40
Status:
Type:
Resolution
Passed
File created:
In control:
4/6/2021
Clerk of the Board
On agenda:
Final action:
4/6/2021
4/30/2021
Enactment date:
4/30/2021
169-21
Enactment #:
Title:
Resolution approving Modification No. 3 to Contract CN 1266-2, Design Review, Software,
Implementation and Testing Services for an Advanced Train Control System (ATCS) for the Central
Subway Project, with Thales Transport & Security Inc., to modify ATCS software and designs to
conform to national fire codes, correct track speed limits, modify installation requirements, accelerate
completion of work, and compensate Thales for costs and impacts it incurred arising from delay to the
Project, increasing the contract amount by $12,831,743.60 for a modified contract amount of
$27,730,300.40; to extend the substantial completion of the ATCS by 670 days for a total contract
term of December 3, 2013, through April 29, 2022, and to extend the contract warranty period to April
29, 2025, to commence upon approval by the Board of Supervisors.
Sponsors:
Attachments:
1. Leg Ver1, 2. DRAFT Contract Mod No. 3, 3. Original Contract 120313, 4. Contract Mod No. 1
120319, 5. Contract Mod No. 2 021921, 6. MTAB Resolution 210406-043, 7. MTA Briefing Ltr 032421,
8. MTA Ltr 032621, 9. Form 126, 10. BLA Report 042121, 11. Comm Pkt 042121, 12. MTA
Presentation 042121, 13. Board Pkt 042721, 14. Form 126 Final, 15. Leg Final
Action By
Date
Action
Result
Ver.
RECEIVED FROM DEPARTMENT
Clerk of the Board
3/29/2021
1
RECEIVED AND ASSIGNED
President
4/6/2021
1
RECOMMENDED
Budget and Finance Committee
4/21/2021
1
Pass
ADOPTED
Board of Supervisors
4/27/2021
1
Pass
APPROVED
Mayor
4/30/2021
1