Title:
|
Resolution approving Modification No. 3 to Contract CN 1266-2, Design Review, Software, Implementation and Testing Services for an Advanced Train Control System (ATCS) for the Central Subway Project, with Thales Transport & Security Inc., to modify ATCS software and designs to conform to national fire codes, correct track speed limits, modify installation requirements, accelerate completion of work, and compensate Thales for costs and impacts it incurred arising from delay to the Project, increasing the contract amount by $12,831,743.60 for a modified contract amount of $27,730,300.40; to extend the substantial completion of the ATCS by 670 days for a total contract term of December 3, 2013, through April 29, 2022, and to extend the contract warranty period to April 29, 2025, to commence upon approval by the Board of Supervisors.
|